A man completes building a House in 5 days.... 3 men will complete building the house in..... Days.
Answers
Answer:
If 10 workers need 3 days to build 1 house then 1 worker needs 3 x 10 = 30 days to build 1 house.
So rate of work is 1 house / 30 worker days effort
So with 15 workers you get this 30 worker days effort in 30/15 = 2 days
So 15 workers would need 2 days to build a house
At this rate, to build 4 houses 15 workers need 4 x 2 = 8 days.
But this is if life was only maths. In real life 15 workers may take more time than 10 workers due to other factors like relevant skill set & team coordination.
PS: hope that am not doing someone's homework here
Step-by-step explanation:
M1*D1*W2 = M2*D2*W1
10*3*4 = 15*x*1
X = 30*4/15
X = 8
So 8 workers are required
time taken by a man to complete 1 building=5 days
rate of doing work by 1 man =1/5
So the time taken to complete 1 building by 3 workers is = 5/3 days