A man completes full work in 10 days, he completes 2/3 work in 8 days and 1/3 on 9th day. How much he does on 10th day?

Answers

Answered by inhumandrowsey
0

work done in 8 days = 2/3

work done on 9th day = 1/3

total work in 9 days = 2/3 + 1/3 = 3/3 = 1

so he completed his work on 9th day and no work was left to be done on the 10th day