A man do a work in 12 days working 8 h/day. If he does 6h/day, what would be the number of days taken by him
Answers
Answered by
6
12 days working 8 hr / day
1 days working 12/8 = 3/2
6hr / day = 3/2 × 6 = 9 days
Answered by
20
Total hours is equal to 12 into 8 that is 96
if we do work 6 hours daily then total hours divided by 6 that is 96 by 6 is equal to 16 days .
16 days he will complete his work