a man do a work in 12 days working 8 hour they if he does 6 hour a day what would be the number of days taken by him
Answers
Answered by
1
Answer. It will take 16 days to complete the same work.
Answered by
0
Step-by-step explanation:
It will take 16 days to complete the same work.