A man do a work in 12 days working
8h/day. If he does 6 h/ day, what would
be the number of days taken by him?
please explain the process
Answers
Answered by
1
Answer:
he will take 16 days working 6h/day
Step-by-step explanation:
(12×8)÷6
Answered by
1
Answer:
A mam do a work in 12 days working 8 hour and if he work 6 hour so the number of days taken by him is 10 day because he work 6 hour in a day