A man does .2 of a piece of work on the first day, .15 on the second and .07 of it
on the third day. How much of the work remains undone?
Answers
Answered by
1
Answer:
The answer to your question is 8
Answered by
3
Answer:
0.58
Step-by-step explanation:
We can say that the total amount of work is 1
So then we substrat the pieces of work from 1
1 - 0.2 = 0.8
0.8 - 0.15 = 0.65
0.65-0.07 = 0.58
Hope this helps!