A man need 21 days to complete 7/8 of a work, how many mored ays he need to complete the work if the quantum of work is increased by 50℅
Answers
Answered by
3
Answer:
15 days
Step-by-step explanation:
time = total work / efficiency
Total work is not given but the part work is given.
We need to find total time first.
21 = x * (7/8)
21 * 8/7 = x
x = 24 days
If total work increases by 50%, time will also increase by 50% because efficiency is same.
Increase 24 by 50% = 24 + 12 = 36 days
36 days - 21 days (given in que.) = 15 days
Answered by
0
Given,
The number of days in which work is done
The quantum of work increased in percentage
Solution,
Formula used,
Assume that the efficiency of the man is x.
Therefore,
Now according to the question,
Therefore, the number of days required is
Hence, the required number of days are
Similar questions