a man takes 10 days to finish a job were as a women takes 6 days to finish a same job . together they worked for 3 days and then the women left. in how many days will the man complete the remaining work
Answers
The man will complete the remaining work in 2 days, if the the man and woman had worked together for 3 days and after 3 days the woman had left.
Step-by-step explanation:
A man takes 10 days to finish a job
So, work done by the man in 1 day =
A women takes 6 days to finish the same job
So, work done by the women in 1 day =
It is given that together they have worked for 3 days
∴ The work done by man and women together in 3 days will be,
= 3 * []
= 3 * []
=
=
∴ The remaining work to be done by the man after the women left,
= 1 -
=
Since the man can finish 1 job in 10 days
Then, th of the job or the work will be finished by the man alone in,
=
= 2 days
Thus, the man will complete the remaining work in 2 days.
----------------------------------------------------------------------------------------------
Also View:
A and B working together can do a work in 6 days. if A takes 5 days less than B to finish the work in how many days B alone can do the work ?
https://brainly.in/question/8587762
Manish takes 9 days more than his father to do a certain piece of work together they can do the work in 6 days •how many days will Manish take to do that work alone?
https://brainly.in/question/14532722