Math, asked by krishnaking8165, 1 year ago

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ? (a) 75 (b) 85 (c) 100 (d) 120

Answers

Answered by sprao534
0
Please see the attachment