Math, asked by dineshbehra433, 5 months ago

A man works for 10 hours in a day and completes a job in 16 days. In how many days will he complete the same job if he works for 8 hours in a day?

Answer step by step.​

Answers

Answered by ymovva2008
2

Answer:

20

Step-by-step explanation:

10x16=160

160/8=20

Answered by aanyasrivastava24dec
9

Answer:

20days

Step-by-step explanation:

by inverse proportion

10/16=8/x

160=8x

=20days

hope u like my answer

Similar questions