A man works twice as fast as a woman. A woman works twice as
fast as a boy. If 16 men can complete a job in 12 days, how many days
would be required for 32 women and 64 boys together to complete the
same job?
Answers
Answered by
8
Answer:
32 women will finish the job in 48 days and 64 boys will finish the job in 198
Step-by-step explanation:
Answered by
1
In 12 days, 16 men do a job.
So work done by 16 men together in a single day=
Work done by a man in a single day=
A man work twice as fast as a woman. In other words, a woman work half as fast as a man
Work done by women in a single day
A woman work twice as fast as a child. In other words, child work half as fast as a woman
Work done by a child in a single day
Net work done by 32 women and 64 boys together in a single day===
Time taken by them to work together= days
Marking me brainliest would surely have no efforts to put on...
#LoveToHelp