A mason can build a wall in 4days working at the rate of 6hours per day will he build the wall working at the rate of 8 hours per day
Answers
Answered by
1
Answer:
3 days
.....................
Answered by
0
Answer:
3 days
Step-by-step explanation:
here it is in indirect proportion.
4:6::8:?
= 4*6 = 8*?
= 24=8*?
=24/8=?
=3