Math, asked by GalwayGirl, 6 months ago

A mason’s helper requires 4 hours more to pave a concrete walk than it takes the mason. The two worked together for 3 hours when the mason was called away. The helper completed the job in 2 hours. How long would it take each to do the same job working alone?​

Answers

Answered by alucardngmunggo
6

Answer

The mason will finish the job in  6 hours while the helper will be finished in 10 hours.

Step-by-step explanation:

Mason does job in m hours. Helper does job in m+4 hours.

t=time in hrs

1/m + 1/(m+4)=(2m+4)/(m^2+4m) = 1/t

3 * (2m+4)/(m^2+4m) = (6m+12)/(m^2+4m) = 3/t

1 - (6m+12)/(m^2+4m) time remaining [1 - 3/t]

2 * 1/(m+4)= 1 - (6m+12)/(m^2+4m)

2/(m+4)=1 - (6m+12)/(m(m+4))

 

2m=m^2+4m-6m-12

m^2-4m-12=0

(m-6)(x+2)=0

m=6 hr

m+4=10 hr

Answered by amitnrw
1

Given : A mason’s helper requires 4 hours more to pave a concrete walk than it takes the mason.

The two worked together for 3 hours when the mason was called away. The helper completed the job in 2 hours.

To Find : How long would it take each to do the same job working alone?​

Solution:

Mason complete the job alone in   x hrs

Then Helper completed the job alone in x  + 4 hrs

1 hr work   of Mason  = 1/x  

1 hr work of helper = 1/(x + 4)

Mason worked for 3 hrs , and helper worker for (3 + 2) = 5 hrs

Total Work done

3/x  + 5/(x + 4) = 1

=> 3(x + 4) + 5x  = x(x + 4)

=> 3x + 12 + 5x = x² + 4x

=> x²  - 4x - 12 = 0

=>  (x - 6)(x + 2) = 0

=> x = 6        (x = -2 not possible )

x + 4 = 6 + 4 = 10

Mason complete the job alone in   6  hrs

Helper completes the job alone in 10 hrs

Learn More:

with P starting the work, working on alternate days P and Q can

brainly.in/question/12303996

With p starting the work, working on alternate days, p and q can ...

brainly.in/question/12364364

Similar questions