a mat of length 180 m is made by 15 women in 12 days .how long will it take for 32 women to make a mat bof length 512?
Answers
Answered by
7
- find the area of abcd find the area of the shaded reagion
Answered by
29
Therefore it will take 16 days for 32 women to make a mat of length 512 m.
Step-by-step explanation:
We are using the following formula to solve the problem,
Here M₁ and M₂ = the number of workers
d₁ and d₂ = the number of days
w₁ and w₂= amount of work.
Here M₁= 15 women, d₁=12 days and w₁= 180 m
M₂= 32 women , d₂= ? and w₂= 512 m
Putting the all values in the above equation
Therefore it will take 16 days for 32 women to make a mat of length 512 m.