Business Studies, asked by ayushirohilla1234, 4 months ago


A network is developed by starting with a list of activities and their?
(A) Immediate successors
(B) Immediate connectors
(C) Immediate predecessors
(D) Immediate precursors​

Answers

Answered by wajahatkincsem
2

Option C is correct.

Immediate Predecessors.

Explanation:

  • When starting a critical path method, it is important to analyze activity, immediate predecessors, and the duration.
  • When doing the experiment, it is important to add the activity on the arc along with the duration.
  • All these steps are important for project management.
  • For the success of the project, this is important to analyze activities and their immediate predecessors.