Math, asked by varshitabamola, 19 days ago

A piece of work by A in 25 days and B in 20 days. A and B works together for 5 days, after that A leaves. In how many days B will finish the remaining work?

Answers

Answered by aarya324
1

Answer:

Correct option is

B

11 days

Step-by-step explanation:

A's 1 day's work =

25

1

Similarly, B's 1 day's work =

20

1

A's and B's together 1 day's work

25

1

+

20

1

=

100

4

+

100

5

=

100

4+5

=

100

9

Their 5 day's work together = 5 x 1 day's work

1−

100

45

=

100

100

100

45

=

100

100−45

=

100

55

Now, this remaining work is done by B.

Let B takes x days to complete it.

20

1

×x=

100

55

⇒x=

100

55

×20

⇒x=

5

55

⇒x=11

Hence, B will finish the remaining work in 11 days