A piece of work can be completed by 45 men in 90 days. If only 30 men are available,how many days will it take to complete the same work
Answers
Answered by
0
Answer:
85
Step-by-step explanation:
Answered by
0
Answer:
135 days
Step-by-step explanation:
90×45/30=3×45=135 days