A piece of work can be completed by 45 men in 90 days. If only 30 men are available how many days will it take to complete the same work
Answers
Answered by
0
No. of men 45 30
days 90 x
x1y1 = x2y2x1y1=x2y2
45×90=30×x
45×90/30=x
45×3=x
135 days=x
Answered by
1
Answer:
No. of men 45 30
days 90 x.
x1y1 = x2y2x1y1=x2y2.
45×90=30×x.
45×90/30=x.
45×3=x.
x = 135 days.