a pirce of road is constructed by 84 worker in 36 days .how much more worker would be required to finished the same work in 21 days
Answers
Answered by
2
Answer:
60
Step-by-step explanation:
number of workers and number of days required to finish the work are inversely proportional
now let X be the required number of workers
so 84 workers did the work in 1/36 days
X workers did the work in 1/26 days
84/26=X/36
X=(84*36)/21
X=(84*12)/7
X=12*12
X=144
so total 144 members are required
but already 84 members are working
so 144-84=60
60 more workers are required to finish the work in 21days