Business Studies, asked by sravyalucky1119, 8 months ago


A power plant has to meet the following load demands:
Load A: 60 MW from 8 AM - 6 PM
Load B: 50 MW from 6 AM - 10 AM
Load C:30 MW from 7 AM - 12 PM
Load D:20 MW from 6 PM - 10 PM
Load E: 10 MW from 10 AM - 6 AM
The coincidence factor for the above plant is:
a. 0.70 -0.74
b. 0.75 -0.79
c. 0.80 -0.84
d. 0.85 -0.89​

Answers

Answered by sravan1487
4

Answer:

load a.

Explanation:

d.0.85-0.89

please make brilliant and follow me and like me

Similar questions