Math, asked by hiteshrobby, 10 months ago

A process has a lower specification limit and no upper limit. The current process yield has 0.39% of everything below the lower limit. What is the capability (Cpk) of this process. options: 2.66 0.89 2.84 1.67

Answers

Answered by amitnrw
0

Given :  A process has a lower specification limit and no upper limit. The current process yield has 0.39% of everything below the lower limit

To find : capability (Cpk) of this process.  

Solution:

The current process yield has 0.39% of everything below the lower limit

z score = -2.66

Z score = ( Value - Mean) / SD

=> -2.66 = ( Value - Mean) / SD

=> 2.66 = ( Mean - Value )/SD

Dividing both sides by 3

=> 0.886 = ( Mean - Value )/3SD

Cpk = (Mean - LSL)/3SD

=> Cpk = 0.886 = 0.89

capability (Cpk) of this process. is 0.89

Learn more:

Assume that the diameter of 1000 brass plugs taken consecutively ...

https://brainly.in/question/9237067

Assume that adults have iq scores that are normally distributed with ...

https://brainly.in/question/11133397

Attachments:
Similar questions