A Project consists of 16 activities having their predecessor relationship as follows:

i.

A is the first activity of the project.

ii.

B, C and D follow A and can be done concurrently.

iii.

E and G Cannot begin until C is completed, and can be performed simultaneously.

iv.

F is the immediate successor to activities B and E.

v.

H and K run in parallel, both succeed G.

vi.

L succeeds F and H.

vii.

I and J are immediate successor activities to activity D.

viii.

M and N are immediate successor to I and K. However, both M and N can be performed

concurrently.

ix.

Activities O and P are the last activities. Activity O is the immediate successor to N and L.

Activity P is the immediate successor to M and J. Draw the network and number the events​

Answers

Answered by shahfaisal43
4

Answer:

A Project consists of 16 activities having their predecessor relationship as follows:

i.

A is the first activity of the project.

ii.

B, C and D follow A and can be done concurrently.

iii.

E and G Cannot begin until C is completed, and can be performed simultaneously.

iv.

F is the immediate successor to activities B and E.

v.

H and K run in parallel, both succeed G.

vi.

L succeeds F and H.

vii.

I and J are immediate successor activities to activity D.

viii.

M and N are immediate successor to I and K. However, both M and N can be performed

concurrently.

ix.

Activities O and P are the last activities. Activity O is the immediate successor to N and L.

Activity P is the immediate successor to M and J. Draw the network and number the events

A Project consists of 16 activities having their predecessor relationship as follows:

i.

A is the first activity of the project.

ii.

B, C and D follow A and can be done concurrently.

iii.

E and G Cannot begin until C is completed, and can be performed simultaneously.

iv.

F is the immediate successor to activities B and E.

v.

H and K run in parallel, both succeed G.

vi.

L succeeds F and H.

vii.

I and J are immediate successor activities to activity D.

viii.

M and N are immediate successor to I and K. However, both M and N can be performed

concurrently.

ix.

Activities O and P are the last activities. Activity O is the immediate successor to N and L.

Activity P is the immediate successor to M and J. Draw the network and number the eventsA Project consists of 16 activities having their predecessor relationship as follows:

i.

A is the first activity of the project.

ii.

B, C and D follow A and can be done concurrently.

iii.

E and G Cannot begin until C is completed, and can be performed simultaneously.

iv.

F is the immediate successor to activities B and E.

v.

H and K run in parallel, both succeed G.

vi.

L succeeds F and H.

vii.

I and J are immediate successor activities to activity D.

viii.

M and N are immediate successor to I and K. However, both M and N can be performed

concurrently.

ix.

Activities O and P are the last activities. Activity O is the immediate successor to N and L.

Activity P is the immediate successor to M and J. Draw the network and number the events

Explanation: