A Project consists of 16 activities having their predecessor relationship as follows:
i.
A is the first activity of the project.
ii.
B, C and D follow A and can be done concurrently.
iii.
E and G Cannot begin until C is completed, and can be performed simultaneously.
iv.
F is the immediate successor to activities B and E.
v.
H and K run in parallel, both succeed G.
vi.
L succeeds F and H.
vii.
I and J are immediate successor activities to activity D.
viii.
M and N are immediate successor to I and K. However, both M and N can be performed
concurrently.
ix.
Activities O and P are the last activities. Activity O is the immediate successor to N and L.
Activity P is the immediate successor to M and J. Draw the network and number the events
Answers
Answer:
A Project consists of 16 activities having their predecessor relationship as follows:
i.
A is the first activity of the project.
ii.
B, C and D follow A and can be done concurrently.
iii.
E and G Cannot begin until C is completed, and can be performed simultaneously.
iv.
F is the immediate successor to activities B and E.
v.
H and K run in parallel, both succeed G.
vi.
L succeeds F and H.
vii.
I and J are immediate successor activities to activity D.
viii.
M and N are immediate successor to I and K. However, both M and N can be performed
concurrently.
ix.
Activities O and P are the last activities. Activity O is the immediate successor to N and L.
Activity P is the immediate successor to M and J. Draw the network and number the events
A Project consists of 16 activities having their predecessor relationship as follows:
i.
A is the first activity of the project.
ii.
B, C and D follow A and can be done concurrently.
iii.
E and G Cannot begin until C is completed, and can be performed simultaneously.
iv.
F is the immediate successor to activities B and E.
v.
H and K run in parallel, both succeed G.
vi.
L succeeds F and H.
vii.
I and J are immediate successor activities to activity D.
viii.
M and N are immediate successor to I and K. However, both M and N can be performed
concurrently.
ix.
Activities O and P are the last activities. Activity O is the immediate successor to N and L.
Activity P is the immediate successor to M and J. Draw the network and number the eventsA Project consists of 16 activities having their predecessor relationship as follows:
i.
A is the first activity of the project.
ii.
B, C and D follow A and can be done concurrently.
iii.
E and G Cannot begin until C is completed, and can be performed simultaneously.
iv.
F is the immediate successor to activities B and E.
v.
H and K run in parallel, both succeed G.
vi.
L succeeds F and H.
vii.
I and J are immediate successor activities to activity D.
viii.
M and N are immediate successor to I and K. However, both M and N can be performed
concurrently.
ix.
Activities O and P are the last activities. Activity O is the immediate successor to N and L.
Activity P is the immediate successor to M and J. Draw the network and number the events
Explanation: