A project manager needs to determine the probability of completing a project in 80 days or less. The expected project duration is 65 days with a standard deviation of 9 days.What is the
the probability for completion of project in the specified time?
a) 50%
b) 95%
c) 99%
d) None of the above
Answers
Answered by
8
Answer:
c) 99%
Explanation:
please follow me and put brainlest thank and put star please
Answered by
0
Answer:
99%
Explanation:
the probability is 99%