a project manager needs to determine the probability of completing a project in 80 days or less. the expected project duration is 65 days with a standard deviation of 9 days . what is the probability for completion of project in the specified time ?
A-50%
B-95%
C-99%
D- NON OF THE ABOVE
Answers
Answered by
2
Answer:
Correct option is c-99%