Math, asked by PinkSunshine6087, 7 months ago

A public sewer line is being installed along 80 1/4 m of road. The supervisor says
that the labours will be able to complete 7.5 m in one day. How long will the
project take to complete?

Answers

Answered by Jo2420
7

Answer:

Step-by-step explanation:

total length of the road= 80 1/4 m

total length labourers can complete in a day= 7.5m

total days it will take to complete= 80 1/4 ÷ 7.5 =10.7 = 11 days

Answered by Aripthajoysce120735
3

Answer:

The length of sewer line to be installed: 80 1/2 m

The length of sewer line installed in one day: 7.5 m

Time to complete installation- ?

Time is equal to total length / length installed per day:

So time= 80 1/2 m/ 7.5 m

80 1/2 m = 161/2 m and 7.5 m = 15/2 m

(161/2)/(15/2)= 161/15 = 10 11/15 days ≈ 11 days as it takes most of day 11

Answer is 11 days