A public sewer line is being installed along
82 m of road. The supervisor says that
the labourers will be able to complete 7.5 m
in one day. How long will the project take to
complete?
Solution:
Answers
Answered by
3
Hêy Fríèñd....
Here is the Solution..
In one day = 7.5 m
No. of days taken to complete 82m = 82/7.5
.
Ans.= 10.9
Hence , It will take 11 days.
..
.
.
.
.
.