A risk that has become reality in your project has led to a cost increase. You have already used the funds reserved to handle this risk and have concluded that you need additional funds that the project does not have. Who is the most likely person or group you need to ask for help?

Answers

Answered by kennedyngoziviolet
19

Answer:

your organization management team

Explanation:

Answered by blondie33579
14

Answer:

Explanation:

To compress the schedule, project managers start with fast-tracking because it does not cost more. However, it increases risk as activities are overlapping.