A risk that has become reality in your project has led to a cost increase. You have already used the funds reserved to handle this risk and have concluded that you need additional funds that the project does not have. Who is the most likely person or group you need to ask for help?
Select an answer:
your organization's management team
the project customer
the project sponsor
the project stakeholders