Math, asked by supramathapa, 8 months ago


A road construction crew is resurfacing the highway between point D and point
E. The distance between point D and point E is 93 miles of road. The crew has
completed 35 miles. If they work at a pace of 2.9 miles per day, how many
more days will it take to finish?

21
54
35
20​

Answers

Answered by uniqueinsaan0
2

Answer:

20

Step-by-step explanation:

v = 2.9 miles per day

t = the number of days needed to finish

The have d = 93 - 35 = 58 miles to finish.

Since v = d/t we have

58/t = 2.9

t = 20 days. It will take 20 days more to finish the road.