A school would like to build a bicycle shed.The local contractor has said that 5 workers can build the shed in 8 days.All workers work at the same rate. (1)How many workers would be needed if the shed is to be built in 5 days?(2)if the school gets only 4 workers,how many days will it take to build the shed?
Answers
Answered by
2
Answer:
(1.) 2 workers (2).7days
Step-by-step explanation:
rachealmenendez12:
pls show wrking out