Math, asked by prefect3742, 1 year ago

A six men working 10 hours a day can do a piece of work in 24 days .in how many days will 9 men working for 8 days do the same work

Answers

Answered by Anonymous
2

Answer:


Step-by-step explanation:

6 men=24 days

1 men=(24/6)days

9men=24/6 × 9

9 men=36days

Answered by tamilcholan1995
2

Answer:20

Step-by-step explanation:

1day work =10*6 =60

Total work --> 24*60=1440

9*8=72

1440/72=20