A small–scale company undertakes an agreement to make 540 motor pumps in 150 days

and employs 40 men for the work. After 75 days, the company could make only 180

motor pumps. How many more men should the company employ so that the work is

completed on time as per the agreement?​

Answers

Answered by Anonymous
7

The number of more employees needed is 40.

•Given data :

Total pump to make = 540

Total time for the agreement = 150 days

40 men made 180 pumps in 75 days

• So,the remaining number of pumps to make = (540-180) = 360 pumps

• Remaining number of days for the agreement = (150-75) = 75 days

• Now,

In 75 days 180 pumps are made by = 40 men

In 75 days 1 pump is made by = 40/180 men ( direct proportion)

In 75 days 360 pumps are made by = 40×360/180 = 80 men (direct proportion)

• The amount of more men

= Necessary men - Current men

= 80 - 40

= 40

The company needs 40 more men to finish the agreement in the given time. (Answer)