A standard takt time for preparing a burger is 5 minutes. All the burger orders are fulfilled in the given time, then

O a. Cycle time is definitely not more than Takt time

O b. Cycle time is definitely more than Takt time

O c. Time is not enough

O d. Takt time is definitely not more or not equal to Cycle time

Answers

Answered by pratikrathod406508
0

Answer:

b . cycle time is definitely more than takt time

coz burger is ready and fulfilled to order therefore

hope it is useful u you