A takes 10 days less than the time taken by B to finish
a piece of work. If booth A and B together can finish the
Work in 12 days, find the time taken
by
B to finish the
work
Answers
Answered by
0
10 days time taken by the Booth B
Answered by
8
Solution :
Let B take time on a piece of work be r day
A take time on a piece of work be (r - 10) day
⇒ B work done in one day = 1/r
⇒ A work done in one day = 1/r-10
If both A & B together finish the work in 12 day's, so for one day;
⇒ A + B = 1/12
As we know that given quadratic polynomial compared with ax² + bx + c;
- a = 1
- b = -34
- c = 120
Now;
∴ x = 4 when we put the place of A value come's negative so it's not acceptable .
Thus;
Time taken by B to finish the worked = 30 day's .
Similar questions