A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work alone. What are the moral values reflected in this question which are to be adopted in our life?
Answers
Answered by
442
Let's B alone take x days to finish the work.
B’s 1 days work = 1/x
A alone can finish the work in = x - 10
A’s 1 days work= 1/(x-10)
Given: A and B together can finish the same work in 12 days.
(A and B)'s 1 days work = 1/12
A’s 1 days work + B’s 1 days work = 1/x + 1/(x-10)
ATQ
1/x + 1/(x-10) = 1/12
(x-10) + x / x(x-10) = 1/12
x-10 + x / x² -10x = 1/12
2x -10 / x² -10x = 1/12
12(2x -10) = x² -10x
24x -120 = x² -10x
x² -10x -24x +120= 0
x² -34x +120= 0
x² 30x -4x +120= 0
x( x -30) -4(x -30)= 0
(x-30)(x-4)= 0
(x-30) = 0 or (x-4)= 0
x = 30 or x= 4
The value of x cannot be less than 10, so x= 30
Hence, the time taken by B to finish the work in 30 days.
The moral values reflected in this question which are to be adopted in our life is UNITY.
HOPE THIS WILL HELP YOU...
B’s 1 days work = 1/x
A alone can finish the work in = x - 10
A’s 1 days work= 1/(x-10)
Given: A and B together can finish the same work in 12 days.
(A and B)'s 1 days work = 1/12
A’s 1 days work + B’s 1 days work = 1/x + 1/(x-10)
ATQ
1/x + 1/(x-10) = 1/12
(x-10) + x / x(x-10) = 1/12
x-10 + x / x² -10x = 1/12
2x -10 / x² -10x = 1/12
12(2x -10) = x² -10x
24x -120 = x² -10x
x² -10x -24x +120= 0
x² -34x +120= 0
x² 30x -4x +120= 0
x( x -30) -4(x -30)= 0
(x-30)(x-4)= 0
(x-30) = 0 or (x-4)= 0
x = 30 or x= 4
The value of x cannot be less than 10, so x= 30
Hence, the time taken by B to finish the work in 30 days.
The moral values reflected in this question which are to be adopted in our life is UNITY.
HOPE THIS WILL HELP YOU...
Answered by
110
Answer:
Step-by-step explanation:
Solution :-
Let B will take x days to complete the work.
Work done by B in 1 day = 1/x
And A will complete the work = x - 10
Work done by A in 1 day= 1/(x - 10)
According to the Question,
⇒ 1/x + 1/(x - 10) = 1/12
⇒ 2x - 10/x² - 10x = 1/12
⇒ 12(2x - 10) = x² - 10x
⇒ 24x - 120 = x² - 10x
⇒ x² - 10x - 24x + 120 = 0
⇒ x² - 34x + 120 = 0
⇒ x² 30x - 4x + 120 = 0
⇒ x( x - 30) - 4(x - 30) = 0
⇒ (x - 30) (x - 4) = 0
⇒ x - 30 = 0 or x - 4 = 0
⇒ x = 30, 4 (Neglecting 4)
⇒ x = 30
Hence, the time taken by B to finish the work in 30 days.