A takes 10 days less than the time taken by B to finish a piece of work. If both A and B
together can finish the work in 12 days, find the time taken by B to finish the work.
Answers
Answered by
0
Answer:
Step-by-step explanation:
Let B alone finish the work =xdays.
And A alone finish the work =(x−10)days
A' s one day work = 1/(x-10)
B's one day work = 1/x
As it given that
(A+B) can finish work in 12 days
∴(A+B) one day work= 1/12
⇒A ′ s one day work +B ′ s one day work=1/12
⇒ 1/x−10 + 1/x = 1/12
⇒x+x−10 / x(x−10) = 1/12
⇒ 2x−10 / x(x−10) = 1/12
⇒12(2x−10)=x(x−10)
⇒24x−120=x ^2 −10x
⇒x ^2 −10x−24x+120=0
⇒x ^2 −34x+120=0
⇒x ^2 −30x−4x+120=0
⇒x(x−30)−4(x−30)=0
⇒(x−4)(x−30)=0
⇒x=4or x=30
∵if x =4 then A alone can finish the working=(4−10)=−6dayswhichisnotpossible
∴x=30days
B alone can finish work in 30 days
Similar questions