A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
Answers
Answer:
Let's B alone take x days to finish the work.
B’s 1 days work = 1/x
A alone can finish the work in = x - 10
A’s 1 days work= 1/(x-10)
Given: A and B together can finish the same work in 12 days.
(A and B)'s 1 days work = 1/12
A’s 1 days work + B’s 1 days work = 1/x + 1/(x-10)
ATQ
1/x + 1/(x-10) = 1/12
(x-10) + x / x(x-10) = 1/12
x-10 + x / x² -10x = 1/12
2x -10 / x² -10x = 1/12
12(2x -10) = x² -10x
24x -120 = x² -10x
x² -10x -24x +120= 0
x² -34x +120= 0
x² 30x -4x +120= 0
x( x -30) -4(x -30)= 0
(x-30)(x-4)= 0
(x-30) = 0 or (x-4)= 0
x = 30 or x= 4
The value of x cannot be less than 10, so x= 30
Hence, the time taken by B to finish the work in 30 days.
The moral values reflected in this question which are to be adopted in our life is UNITY.
HOPE THIS WILL HELP YOU...
PLZ MARK AS BRIANLIEST,FLW ME AND THX FOR THE SUPERB QUESTION
Answer:
see image for answer
please follow