Math, asked by dhananjay2182, 3 months ago

A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.​

Answers

Answered by ItzBrainlyGirl024
8

Answer:

Let's B alone take x days to finish the work.

B’s 1 days work = 1/x

A alone can finish the work in = x - 10

A’s 1 days work= 1/(x-10)

Given: A and B together can finish the same work in 12 days.

(A and B)'s 1 days work = 1/12

A’s 1 days work + B’s 1 days work = 1/x +  1/(x-10)

ATQ

1/x +  1/(x-10) = 1/12

(x-10) + x / x(x-10) = 1/12

x-10  + x / x² -10x = 1/12

2x -10 / x² -10x = 1/12

12(2x -10) = x² -10x

24x -120 = x² -10x

x² -10x -24x +120= 0

x² -34x +120= 0

x² 30x -4x +120= 0

x( x -30) -4(x -30)= 0

(x-30)(x-4)= 0

(x-30) = 0  or  (x-4)= 0

x = 30  or  x= 4

The value of x cannot be less than 10, so x= 30

Hence,  the time taken by B to finish the work in 30 days.

The moral values reflected in this question which are to be adopted in our life is UNITY.

HOPE THIS WILL HELP YOU...

PLZ MARK AS BRIANLIEST,FLW ME AND THX FOR THE SUPERB QUESTION

Answered by manojchauhanma2
1

Answer:

see image for answer

please follow

Attachments:
Similar questions