A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
Answers
Answered by
0
Let X days be the time taken by B to finish the work.
So,Time taken by A=X-10.
ATQ,X+X-10=12
=>x=11
Therefore time taken by B =11 days.
Please mark it as brainleist.
So,Time taken by A=X-10.
ATQ,X+X-10=12
=>x=11
Therefore time taken by B =11 days.
Please mark it as brainleist.
tanukahlon2:
Sorry this is wrong answer