A takes 2 days to complete one-third of a
Job, B takes 2 days to complete one-sixth
of the same work and C takes 4 days to
complete half the job. If all of them work
together for 2 days and C quits, how long
will it take for A and B to complete the
remaining work done?
5 days
4 days
1 day
2 days
Answers
Answer:
in 2 days is correct answer
Answer:
⇒ therefore the remaining work can be done by A and B in 1 day
Step-by-step explanation:
Given data
A takes 2 days to complete one - third of a job
B takes 2 days to complete one - sixth of the same job
C takes 4 days to complete half of the job
All of them worked together for 2 days after that C quits
The remaining work is completed by A and B together
here we need to find how many days will take A and B to complete the remaining job
Let x be the total work / job
work can be done by A in 2 days =
⇒ work can be done by A in 1 day = =
work can be done by B in 2 days =
⇒ work can be done by B in 1 day = =
work can be done by C in 4 days =
⇒ work can be done by C in 1 day = =
the work can be done A, B and C in 1 day =
= = =
⇒ the total work completed by A, B and C together 2 days =
= 2(the work done by A, B and C in 1 day) = =
the remaining work = = =
⇒ the work can be done by A and B together in 1 day
= = = = which is same as remaining work
⇒ therefore the remaining work can be done by A and B in 1 day