Math, asked by adityasoni3645, 11 months ago

A takes 30 days to complete a job. B takes 20 days to finish the same iob. If they work together, how many days will they take to finish the job

Answers

Answered by tejpalsharma47
1
12 day require to complete the job

adityasoni3645: full solution
adityasoni3645: plz
tejpalsharma47: first of all take LCM of 20&30 it may be 60 now this 60 is the total A and B have to do.. according to this A makes 3 units per day and B makes 2 unit per day Both of them makes 5 per day. Both A and B have to make 60. so they need 12 day