Math, asked by felfela7706, 1 year ago

A takes 5 days more than b to do a certain job and 9 days more than c; a and b together can do the job in same time as

c. How many days a would take to do it?

Answers

Answered by biplabgoswami85
11

Answer:

Let the time taken by C be x days, in which case time taken by A would be x + 9 days, and B would be x + 4 days (5 hours lesser than A)

Now, we're given that the rate of work of A and B (combined) = rate of work of C

1/(x+9) + 1/(x+4) = 1/x

2x+13/(x^2+13x+36) = 1/x

2x^2 + 13x = x^2 + 13x + 36

x^2 = 36

Since the value of days cannot be negative, we get x = 6, and we have to find A which is x + 9 days, i.e. 6 + 9 = 15 days,

Answered by payalchatterje
0

Answer:

C takes 15 days to do the job.

Step-by-step explanation:

Let the day taken by C alone be n

so in one day work done by C= \frac{1}{n}

Time taken by A to do the same work  = n+9 \:  \:  days

So in one day work done by A= \frac{1}{n + 9}

Also A and B can together do the work in same time as C

So work done in one day by A and B together = work done by C in one day

 = \frac{1}{n}

let work done by B in one day be b

 \frac{1}{n}  = b +  \frac{1}{n + 9}

b =  \frac{9}{n(n + 9)}

Hence B takes  \frac{n(n+9)}{9}

days to finish the work alone.

According to Question days taken by A alone = days taken by B alone +5

So, n + 9 =  \:  \frac{n(n+9)}{9 + 5}

solving this  {n}^{2}  = 36

and n=6 days

Hence A alone can do the job in

n+9=6+9=15 days time

Similar questions