A takes 5 days more than b to do a certain job and 9 days more than c; a and b together can do the job in same time as
c. How many days a would take to do it?
Answers
Answer:
Let the time taken by C be x days, in which case time taken by A would be x + 9 days, and B would be x + 4 days (5 hours lesser than A)
Now, we're given that the rate of work of A and B (combined) = rate of work of C
1/(x+9) + 1/(x+4) = 1/x
2x+13/(x^2+13x+36) = 1/x
2x^2 + 13x = x^2 + 13x + 36
x^2 = 36
Since the value of days cannot be negative, we get x = 6, and we have to find A which is x + 9 days, i.e. 6 + 9 = 15 days,
Answer:
C takes 15 days to do the job.
Step-by-step explanation:
Let the day taken by C alone be n
so in one day work done by
Time taken by A to do the same work
So in one day work done by
Also A and B can together do the work in same time as C
So work done in one day by A and B together = work done by C in one day
let work done by B in one day be b
Hence B takes
days to finish the work alone.
According to Question days taken by A alone = days taken by B alone +5
So,
solving this
and n=6 days
Hence A alone can do the job in
days time