⭐A takes 5days less than the time taken by B to do some work. they can do work together in 6 days. Find the number of days in which each of them can do the work separately.⭐
CLASS 10 CHAPTER :QUADRATIC EQUATIONS
❌NO SPAM❌
BEST ANSWER WILL BE MARKED AS BRAINLIEST
Answers
Let the time taken by B to finish the work be 'x'.
Given that A takes 5 days less than the time taken by B.
Hence, A alone can finish the work in (x - 5) days.
Given that they can do work together in 6 days.
Work done by (A + B) in 1-day = (1/6).
Now,
A's one day work + B's one day work = (A + B)'s one day work.
⇒ (1/x - 5) + (1/x) = 1/6
⇒ 6(x + x - 5) = x(x - 5)
⇒ 6(2x - 5) = x^2 - 5x
⇒ 12x - 30 = x^2 - 5x
⇒ x^2 - 17x + 30 = 0
⇒ x^2 - 2x - 15x + 30 = 0
⇒ x(x - 2) - 15(x - 2) = 0
⇒ (x - 2)(x - 15) = 0
⇒ x = 2,15.
If the times it(B) takes is 2 days, then the time taken by A will be -5, which is not possible.
So, consider x as 15.
Then:
⇒ x - 5
⇒ x = 10.
Therefore:
⇒ A alone can finish the work in 10 days.
⇒ B alone can finish the work in 15 days.
Hope it helps!
Answer:
let the A works done be x.
and B be x+5
Step-by-step explanation:
6(1/x+1/x+5)=1
1/x+1/x+5=1/6
x+x+5/x(x+5)=1/6
6x +6x+30=x^2+5x
-x^2+10x-3x+30
-x(x-10)-3(x-10)
-(x-3)(x-10)
-x=3 &x=10
a =10
b= x+5= 15