A takes 6 days and B takes 4 days to complete a work

A's 1 Day work = 1/6

B's 1 Day work = 1/4

A + B together 1 Day work =  1/6 + 1/4

= (2 + 3)/12

= 5/12

A's 4 Day work  = 4/6 = 2/3

Remaining work = 1 - 2/3  = 1/3

Number of Days  more time A & B will Take =  (1/3)/(5/12)

= 12/15

= 4/5

= 0.8 Days