Math, asked by arpita705, 11 months ago

A takes 6 days less than B to do a work. If both A and B working together can do it in 4 days, how many
days will B take to finish it ?

Answers

Answered by msSINGLE
0

\huge{\fbox{\fbox{\bigstar{\mathfrak{\pink{♡Single♡}}}}}}

We call the time it takes for B to finish the piece of work = x

So , work can be done in 1 day = ?

1/x + 1/x-6 = 1/4

x-6 / x(x-6) + x / x(x-6) = 1/4

4(x-6+x) = - 6x

4( 2x - 6) = - 6x

8x - 24 = - 6x

0 = - 14x + 24

x = ( x - 12 ) ( x - 2 )

x = 12 and 2

If the time it takes B = 2 days then

the time it takes A = 4 days

:. It would take B a period of 12 days to finish the job .

Answered by VishalSharma01
46

Answer:

Step-by-step explanation:

Solution:-

Let B complete work in x days.

And A takes x - 6 days to complete it.

According to the Question,

1/(x - 6) + 1/x = 1/4

⇒ x + x - 6/x(x - 6) = 1/4

⇒ 4(2x - 6) = 2(x - 6)

⇒ 8x - 24 = x² - 6x

x² - 14x + 24 = 0

⇒ x² - 12x - 2x + 24 = 0

⇒ x(x - 12) - 2(x - 12) = 0

⇒ (x - 2) (x - 12) = 0

x = 2, 12 (Neglecting x = 2 as A takes x - 6 days)

x = 12

Hence, B takes 12 days to complete the work.

Similar Questions :- [Click on the links]

https://brainly.in/question/305673

https://brainly.in/question/2773345

https://brainly.in/question/3068855

https://brainly.in/question/304589

https://brainly.in/question/936370

Similar questions