Math, asked by soumuatus4194, 10 months ago

A takes 6 days less than B to finish a piece of work. If both A and B together can finish the work in 4 days, find the time taken by B to finish the work. (A)12 days (B) 12 ½ Days (C) 13 days (D) 15days

Answers

Answered by kniharikareddi
1

Answer:

A

Step-by-step explanation:

so, lets assume b completes work in x days

and a takes x - 6 days

1/x + 1/(x-6) = 1/4

(( x - 6 + x) / x(x-6)) = 1/4

(2x - 6 / x^2 - 6x ) = 1/4

8x - 24 = x^2 -6x

x^2 -14x + 24 = 0

solving we get x = 12 and 2

so from the given options A is the solution

Answered by sourya1794
49

\bf{\underline{Given}}:-

  • A takes 6 days less than the time taken by B to finish a piece of work.

  • If both A and B together can finish it in 4 days.

\bf{\underline{To\:Find}}:-

  • The time taken by B to finish the work

\bf{\underline{Solution}}:-

Let B alone takes x day to finish the work

and A alone can finish it in ( x - 6) days.

B's 1 day's work = \rm\dfrac{1}{x}

A's 1 day's work = \rm\dfrac{1}{(x-6)}

(A + B)'s 1 day's work = \rm\dfrac{1}{4}

According to the question,

\rm\:\dfrac{1}{x}+\dfrac{1}{(x-6)}=\dfrac{1}{4}

\rm\longrightarrow\:\dfrac{x-6+x}{x(x-6)}=\dfrac{1}{4}

\rm\longrightarrow\:4(x-6+x)=x(x-6)

\rm\longrightarrow\:4x-24+4x={x}^{2}-6x

\rm\longrightarrow\:8x-24={x}^{2}-6x

\rm\longrightarrow\:{x}^{2}-14x+24=0

\rm\longrightarrow\:{x}^{2}-12x-2x+24=0

\rm\longrightarrow\:x(x-12)-2(x-12)=0

\rm\longrightarrow\:(x-12)(x-2)=0

Now,

\rm\:x-12=0

\rm\longrightarrow\:x=0+12

\rm\longrightarrow\:x=12

Then,

\rm\:x-2=0

\rm\longrightarrow\:x=0+2

\rm\longrightarrow\:x=2

Here x cannot be less then 6 so, x = 12

Hence,B alone can finish the work in 12 days.

So, Option (A) 12 days is correct answer.

Similar questions