A takes 6 days less than B to finish a piece of work. If both A and B together can finish the work in 4 days, find the time taken by B to finish the work. (A)12 days (B) 12 ½ Days (C) 13 days (D) 15days
Answers
Answered by
1
Answer:
A
Step-by-step explanation:
so, lets assume b completes work in x days
and a takes x - 6 days
1/x + 1/(x-6) = 1/4
(( x - 6 + x) / x(x-6)) = 1/4
(2x - 6 / x^2 - 6x ) = 1/4
8x - 24 = x^2 -6x
x^2 -14x + 24 = 0
solving we get x = 12 and 2
so from the given options A is the solution
Answered by
49
- A takes 6 days less than the time taken by B to finish a piece of work.
- If both A and B together can finish it in 4 days.
- The time taken by B to finish the work
Let B alone takes x day to finish the work
and A alone can finish it in ( x - 6) days.
B's 1 day's work =
A's 1 day's work =
(A + B)'s 1 day's work =
✫ According to the question,
Now,
Then,
∴ Here x cannot be less then 6 so, x = 12
Hence,B alone can finish the work in 12 days.
So, Option (A) 12 days is correct answer.
Similar questions