A takes 6 days less than B to finish a piece of work. If both A and B together can finish the work in 4 days, find the time taken by B to finish the work.
Answers
Answer:
B-6=A
B-6+B= 4
B=4+6=10
So, B take 10days to finish the work .
Let assume that
Number of days taken by B = x days
So,
Number of days taken by A = x - 6 days
So,
and
Now,
According to statement,
A and B together can take 4 days to finish the work
Hence,
Number of days taken by B = 12 days
and
Number of days taken by B = 6 days
Additional Information
Nature of roots :-
Let us consider a quadratic equation ax² + bx + c = 0, then nature of roots of quadratic equation depends upon Discriminant (D) of the quadratic equation.
If Discriminant, D > 0, then roots of the equation are real and unequal.
If Discriminant, D = 0, then roots of the equation are real and equal.
If Discriminant, D < 0, then roots of the equation are unreal or complex or imaginary.
Where,
Discriminant, D = b² - 4ac