A takes 6 days less than B to finish a piece of work. If both A and B together can finish the work in 4 days, find the time taken by B to finish the work.
Answers
Answered by
0
Answer:
A takes 6 days less than B to finish a piece of work.
Time taken by A = x - 6 days
Time taken by B = x days.
If both A and B together can finish the work in 4 days -
Here x cannot be less than 6, so the x = 2 is invalid.
So, the time taken by B to finish the work = 12 days.
Answered by
0
Answer:
Step-by-step explanation:
a=x-6
b=x
x+x-6=4
2x-6=4
2x=10
x=5
a takes 1 day whereas b takes 5
Similar questions