A takes 6 days less than the time taken by B to complete a work. If they together can complete a work in 4 days find the time taken by each to finish the work ?
Answers
Answered by
0
Suppose B alone takes x days to finish the work. Then A alone can finish it in (x−6) days
Now A's one day's work + B's one day's work =
x
1
+
x−6
1
and (A+B)'s one day's work =
4
1
∴
x
1
+
x−6
1
=
4
1
⇒
x(x−6)
x−6+x
=
4
1
⇒
x
2
−6x
2x−6
=
4
1
⇒8x−24=x
2
−6x
⇒x
2
−14x+24=0
⇒x
2
−12x−2x+24=0
⇒(x−12)(x−2)=0
⇒x=12orx=2
But x cannot be less than 6.
So x=12
Hence, B also can finish the work in 12 days.
Now A's one day's work + B's one day's work =
x
1
+
x−6
1
and (A+B)'s one day's work =
4
1
∴
x
1
+
x−6
1
=
4
1
⇒
x(x−6)
x−6+x
=
4
1
⇒
x
2
−6x
2x−6
=
4
1
⇒8x−24=x
2
−6x
⇒x
2
−14x+24=0
⇒x
2
−12x−2x+24=0
⇒(x−12)(x−2)=0
⇒x=12orx=2
But x cannot be less than 6.
So x=12
Hence, B also can finish the work in 12 days.
Answered by
0
Answer:
no. of days taken by A to finish that work = x
then, no. of days taken by B to finish that work = x+6
now, work done by A in one day = 1/x and work done by B in one day = 1/x+6
now, work done by both A and B in one day,
1/x + 1/x+6 = 1/4
{(x+6)+x}/x(x+6) = 1/4
8x + 24 = x2 + 6x
x2-2x - 24 = 0
x2 -6x +4x -24 = 0
x(x-6) +4(x-6) = 0
(x+4) (x-6) = 0
so, x= 6 (neglecting x = -4)
so, time taken by B to finish the work = x+6 = 12 days
Similar questions