A takes 6 days less than the time taken by b to finish a piece of work if both A and B together can finish it in 4 days find the time taken by b to finish the work

Answers

Answered by sandhya60
2
the answer is 5/12....
Answered by yogesh153
10
A can complete work in=6 days
A can complete work 1 day= 1/6
B=?
A+B together can finish=1/4
(A+B)- A
1/4-1/6
3-2/12
=1/12
THEN RECIPROCAL IT
=12 DAY
B CAN COMPLETE=12 days