Math, asked by PROlearnerO1O1, 3 months ago

A takes 6 days less than the time taken by B to finish a
piece of work. If both A and B working together can finish
the work in 4 days. Find the time taken by A to finish the
work.
..BTA DO AAPKE LIYE TO EASY PEASY H!!!​

Answers

Answered by 1223448
0

Answer:

2 days

Step-by-step explanation: